MARA reported selling about 26,984 BTC for $1.9 billion in the first nine months of the year, then another 13,597 BTC after September at an average price of $81,039. That later sale equaled roughly 40% of its 34,012 BTC holdings at the end of September. The company said it repaid $750 million in Bitcoin-backed borrowing after September, releasing the pledged coins.
MARA’s Nov. 17 filing also details $185 million in senior secured notes issued by its U.S. subsidiary, Long Ridge Energy LLC. The notes carry an 8.75% coupon and mature in 2032. MARA expects the notes and its pending $1.5 billion acquisition of Long Ridge Energy & Power to close together on Nov. 27, subject to customary conditions. Proceeds and cash on hand are intended to help fund the acquisition, repay some existing Long Ridge debt and cover transaction expenses.
The new notes would join $600 million of existing Long Ridge notes with the same coupon and maturity, bringing principal in the series to $785 million. Combined annual coupon payments would be about $68.7 million. Long Ridge operates a 485-megawatt natural gas plant in Hannibal, Ohio, near a MARA mining site. MARA has described the location as a potential high-performance computing campus and said prospective tenants have expressed formal interest. Federal regulators approved the acquisition on Nov. 4.
Riot sold 20,264 BTC for $1.48 billion through September, while mining 4,697 BTC. Its sales were about 4.3 times production, and its holdings dropped from 18,005 BTC at the start of the year to 2,418 BTC on Sept. 30. Riot said it expects, for now, to sell substantially all newly mined Bitcoin to fund data center development, other projects, operating costs and working capital. The company also fully repaid a $200 million credit facility.
Riot’s filing identifies Anthropic as the tenant under a 15-year lease for 910 megawatts of critical IT capacity at its Corsicana campus in Texas. The agreement, signed Oct. 28 and effective Nov. 4, has an initial contract value of about $28 billion, including scheduled rent increases. Riot estimates it will need $5.5 billion in project capital and expects average annual rent of about $1.8 billion. Capacity delivery is expected to begin in June 2027, with the full 910 megawatts available in July 2028.